Combustion vs Hot Gas Path Inspection: What Every Operator Should Know

Written by Michele McDermott, PCM® | CDMP | Nov 16, 2026, 8:18:54 PM

Every gas turbine maintenance plan comes down to two planned events: the combustion inspection (CI) and the hot gas path inspection (HGP). How you scope, time, and bundle them drives availability and lifecycle cost for years afterward. With 2027 outage schedules being set now, the smart move is to treat the two as one strategy instead of two separate line items.

What each inspection covers

The combustor makes the hot gas. The turbine section takes the beating. In F-class machines, firing temperatures run around 2,500°F (1,370°C), and the first-stage buckets carry that heat while spinning at full speed. That combination of thermal and mechanical stress drives major maintenance on the turbine section.

A combustion inspection covers only the combustion section: liners and caps, transition pieces, fuel nozzles, crossfire tubes, flow sleeves, igniters, and flame detectors. No rotor pull is needed, and the outage typically runs 5 to 10 days.

A hot gas path inspection includes the full CI scope, plus Stage 1 nozzles, buckets, and shrouds, later-stage turbine parts, and interstage seals. The upper turbine casing comes off, and the outage typically runs 3 to 6 weeks. 

Combustion Inspection vs. Hot Gas Path Inspection at a Glance

 

Combustion Inspection (CI)

Hot Gas Path Inspection (HGP)

Primary focus

Combustion section only

Combustion section plus turbine section

Components

Liners, transition pieces, fuel nozzles, crossfire tubes

All CI scope plus nozzles, buckets, shrouds, seals

Typical duration

5 to 10 days

3 to 6 weeks

Casing removal

Combustor casing only

Upper turbine casing, and possibly compressor casing

Typical interval

About 8,000 factored hours or about 450 factored starts, varying by OEM and frame 

24,000 to 32,000 factored hours, or about 900 factored starts

Relative cost

Lower

Significantly higher

Upgrade opportunity

Combustion retrofits

Best window: combustion and gas path upgrades together

Typical figures. Actual limits depend on your frame, fuel, duty cycle, and OEM maintenance program.

 

What Drives Your Inspection Interval

Duty profile

Usually governed by

What it means for planning

Baseload

Fired hours

Few starts, so the hours limit arrives first

Intermediate

Hours and starts

Either limit can come first, so track both

Peaker

Starts

The starts limit can trigger several CIs between HGPs

Inspection intervals run on factored fired hours and factored starts, tracked separately. Whichever limit arrives first sets the date. How you dispatch the unit decides which one that is:
  • Baseload units are typically governed by hours.
  • Starts typically govern peakers.
  • Intermediate duty units see a mix, and either limit can come first.

Trips, fast loading, liquid fuel, and high firing temperature all shorten the intervals. A unit that moved from baseload to cycling since its last plan may be due sooner than the calendar says. The HGP range is also moving. With upgraded hot section components and good condition monitoring, 32,000 hours is becoming the target across the industry, which is why 24,000 to 32,000 is the realistic planning range today. OEMs and independent providers both offer interval extension programs, so it is worth comparing what is available for your frame.

Plan to eliminate the CI

The CI and HGP run on different clocks. A cycling unit can reach its CI start limit two or even three times before the HGP comes due. Each one is another outage, another crew, and another set of parts. The fix is to upgrade the combustor at the HGP, so the combustion hardware lasts as long as the hot gas path and the standalone CI goes away on qualifying units.

  • F-class: Hanwha Power's FlameSheet™ combustion system is designed for up to 32,000 hours or 1,250 starts, installs in a standard HGP outage, and delivers sub-9 ppm NOx and CO with hydrogen blending capability.
  • B/E-class: LEC NextGen™ supports up to 32,000 factored hours and 1,200 starts between inspections. GTOP™ packages extend the HGP interval from 24,000 to 32,000 factored hours in Maintenance Mode, with the option to eliminate standalone CIs when paired with compatible combustion hardware.
  • 501F and 7FA: GTOP7 is installable at a standard HGP, and GTOP4 delivers up to 12 to 17% simple-cycle power improvement depending on configuration.

If a CI comes first on your schedule, it is still a good window for a combustion retrofit. The HGP is where you reset the whole cycle.

Questions to ask before your next outage

  • What do borescope data and combustion dynamics say? They tell you whether like-for-like replacement is enough or an upgrade is warranted.
  • How close is the next HGP? If a CI is coming and the HGP is within 12 to 18 months, pulling the HGP forward and bundling the scope may cost less.
  • How does the unit really run? Plan around current dispatch, not the original design assumptions.
  • What does a full plant assessment say? HRSG, steam turbine, and generator limits all shape what an upgrade can deliver.

The bottom line

The two inspections are recurring windows to change the trajectory of your fleet's performance, reliability, and cost. With new turbine prices up 195% and lead times stretching to 2029, every outage on an installed unit is worth more than it was two years ago. Planning your next CI or HGP? Hanwha Power supports operators across GE, Siemens, and Mitsubishi frames with outage planning, combustion retrofits, hot gas path upgrades, and plant assessments. Contact us to talk through your outage strategy. 

References

    • GE Gas Power, GER-3620, Heavy-Duty Gas Turbine Operating and Maintenance Considerations
    • Hanwha Power, FlameSheet™ Combustion System Technical Sales Document (PSM-TS-000050)
    • Hanwha Power, GTOP7 SW501F Upgrade Technical Sales Document (PSM-TS-000044)
    • Hanwha Power, GTOP4.x 7FA Upgrade Technical Sales Document (T00000579)
    • Hanwha Power, LEC III Product Documentation, psm.com
    • Hanwha Power, 7B-EA Products & Solutions Brochure, 2025
    • Hanwha Power, Plant Assessment Brochure, 2025